Independence Middle School Update

Phase 1 – Construction Progress
Phase 2 – Construction Document
& Bidding
High School Concession and Restroom Facility

The Municipality of Bethel Park and the Bethel Park School District are joining forces to construct a restroom and concession stand facility at the turf practice and softball fields on the high school property.
Elementary Center Update

The K-5 elementary project is moving slowly and thoughtfully through the schematic design phase.
Bus Garage Project Update

The bus garage project is also progressing on schedule.
Independence Middle School Update

The Board of School Directors toured the ongoing renovation work at Independence Middle School this week, which included touring the completed office and guidance suite as well as checking-in on the construction work in the sixth-grade wing.
Draw Collective Architectural Plans

Here are the handouts from the August 9, 2022 presentation from Draw Collective
Elementary Center Update

The School District has been engaged in a series of good faith discussions with the property owners at 5631 Kings School Rd
IMS Progress Update



The Board met on July 11 th for a Facilities Committee Meeting of the Whole.
Independence Middle School Photo Updates


Here are some good photos of the work starting at Independence Middle School.
Elementary Center Vote


At their Facilities Committee Meeting on May 8, 2022, the board voted unanimously to construct a new K-5 elementary center on the property at Neil Armstrong Middle School. This means we will eventually close NAMS and all five elementary buildings.