BPSD - Elementary School Project Tentative Precon and Bid Schedule
- 7/31/2023 -DRAW Collective provides MCMS with 85% CD drawings
- 7/312023 – 9/1/2023 -MCMS develops CD estimate and performs a constructability review
- 9/5/2023 -9/15/2023 -Review of CD Estimate & Constructability Review with DRAW Collective and District
- 9/19/2023 – School Board Approved Going Out to Bid
- 9/20/2023 -10/25/2023* -Bid Period
- 10/25/2023 -Bid Day
- 10/26/2023 -11/3/2023 -Selection of Alternates and Scope Review of Low Bidders
- 11/6/2023 -MCMS provides Recommendation of Contractors to District to Award Contracts
- 11/14/2023 -School Board vote to approve awarding contracts
- 11/15/2023 -11/17/2023 -Notices to Proceed Sent and Contracts Issued
- 12/4/2023 -Construction Start
MCMS usually builds in the possibility of extending the bid one week. If this is necessary, the follow dates will apply:
- 9/20/2023 -11 /1 /2023* -Bid Period
- 11/1/2023 – Bid Day
- 11/2/2023 – 11/10/2023 – Selection of Alternates and Scope Review of Low Bidders
- 11/13/2023 – MCMS provides Recommendation of Contractors to District to Award Contracts
- 11/14/2023 – School Board vote to approve awarding contracts
- 11/15/2023-11/17/2023-Notices to Proceed Sent and Contracts Issued
- 12/4/2023 -Construction Start